|
CONSTRUCTION
OVERVIEW
"It's
beginning to look like a railroad out there…"
Civil
and Stations Improvements Contract - Every light rail rider
who comes into Downtown from the south has noticed the progress,
if only subliminally, that has occurred on the Central Platte Valley
Light Rail project over the past month. During the weekend of October
20-21 the first special trackwork was installed in the Central Corridor
tracks. The Light Rail shutdown went off without a hitch. Light
Rail operations commenced after the installation to allow safety
testing well in advance of the first commuters of the morning on
Monday, October 22. Additional weekend shutdowns on November 3-4
and November 10-11 should complete the tie-in between the Central
Corridor and the Central Platte Valley Light Rail extension.
Track
installation between Invesco Field at Mile High Station and Auraria
West Station has progressed well during October. The rail installation
contractor has now completed track from Cherry Creek south to behind
the Auraria Reprographics building. Soon, they plan to work two
crews, one continuing southwards, and one working to the north across
Cherry Creek towards Union Station.
Electrification
work is continuing from Cherry Creek southwards. Heavy electrical
cables are being pulled through the buried conduits into the electrical
vaults. These cables will feed electricity to the overhead contact
wires that power the light rail vehicles. Above ground, the installation
of catenary pole arms, which hold the overhead wires, will begin
soon from Cherry Creek southwards. The three traction-power substations
that will feed electricity to the alignment are in place and being
energized and tested.
Underground
utility installation is now virtually complete. The electricians
are concentrating on signal/communication work throughout the corridor.
The complicated task of connecting signal/communication wiring and
equipment will be continuing until the completion of the project.
Station
shelters have been erected at the Pepsi Center/ Six Flags, Invesco
Field at Mile High, and Auraria Stations, and windscreen masonry
has been started at Auraria Station. These architectural components
add aesthetics to the stations and when complete, will give a finishing
touch to the stations.
Work at Union
Station has progressed well. The Barrel Vault structure has been
erected and foundations for other platform shelters have been installed.
Work in the tunnel is progressing and the addition of the east end
work will tie the tunnel together and make it a very special area.
The
construction contractor has been working most weekends to maintain
the aggressive schedule for completion of the project. Recently,
Walnut Street was closed to traffic to allow work over Friday night/Saturday
to install the rail crossing there. Impact to traffic and pedestrians
was limited and the area was opened on Saturday evening to allow
access for the Bronco's home game on Sunday.
|