![]() Construction Updates |
|
|
During the month
of January the Railroads, and the Line Segment Contractors continued with
grading, bridge construction, and the relocation of the mainlines. |
|
|
The Contractor began working on the Littleton Station Platform and the catenary poles behind Wall "J". Work is progressing with the freight grading for the Electron Lead from Big Dry Creek to just south of Belleview Avenue. The removal of the existing Littleton Interlock and signal system is still needed to complete the final freight grading. |
|
|
The Contractor began work on Lee Gulch this period after getting the Railroadís approval for the shoring. Grading work from the south end of the project to the Littleton Depression also began this month. Progress on the Tufts Flyover continues (see photo to the left). |
|
|
The
Hampden Freight Bridge method of repair was approved in January. The
approved method will be a hydro demolition, which will expose more of
the cut reinforcement steel that will be respliced. In January, the
Contractor finished the abutments for the Oxford LRT Bridge and five
of the six girders were set. The final girder is being recast due to
its quality. The remaining girders are presently being re-inspected
prior to the setting of the final girder. The abutment for the Hampden
LRT Bridge is still under construction. |
|
|
Girders for the Iowa LRT structure were set in January, along with the backwalls, the wingwalls, and the center deck (see photo to the left). LRT grading was complete with the installation of ductbanks from the I-25 and Broadway Station to Florida Avenue. Work progressed on the Iowa Flyover south MSE Wall (as seen in the photo below). |
|
|
In January Track 9,10, and 11 were completed in the Operations Facility site. The Contractor has begun LRT track work in Line Segment 4. The submittal process continues for all items included in the contract. |
|
|
During the month
of January, the Railroads continued on the relocation of the mainlines.
The BNSF continues to work on the middle track alignment in the Interlock
location. In January the UPRR completed the relocation of the southbound
track from Evans Avenue to the Hampden Freight Bridge. Both Railroads
are finalizing the shoo-fly south of Evans to accommodate the delays to
the Hampden Freight Bridge. |
|
|
The Contractor
began work on the OCS and Traction Power substation submittals. Purchase
orders for major material items are being prepared and issued. RTD is
currently reviewing a value engineering proposal from the Contractor to
use electric coded rail for the signal system. A decision will be made
in February. Preliminary layout of cases and identification of basic materials
and components are under way. The contract is
in the process of being closed out and issued final acceptance once all
punch list items have been completed. In January, the
Contractor continued work on the product submittals. PSCo is working on
a temporary OCS work plan with Siemens for the I-25 and Broadway segment. Work continues
with the City and County of Denver (CCD) and the Denver Regional Council
of Governments (DRCOG) as the consultant is preparing for final design
work. The final design is anticipated to be complete by summer and construction
complete by the end of the year. |
|
|
SouthWest
Index | Administration
| Construction Updates
SouthWest Corridor FAQ | General Information |