General Information
The Southwest
Corridor light rail line is a double-track system running from the existing
I-25 and Broadway Station to Mineral and South Santa Fe. It will necessitate
the relocation of existing railroad lines,
and includes construction of 5 stations and 4 park-n-Rides.
The overall
Southwest Corridor LRT project was 85% complete through the end of January
1999. Opening day is currently scheduled for July 14, 2000.
The Southwest
Corridor LRT civil construction is split up into four sections which are
referred to as "line segments." Following the completion of construction
for the four line segments and relocation of the railroads, the RTD contractor
starts layin g light rail tracks. Light rail track installation will be
followed by construction of the electrified overhead contact system and
train signals.
The following
are definitions of the four line segments under construction. For up-to-date
information on the line segments, look at the Construction
Updates page or click on the line segment name.
| Contract
Title: Line Segment 1
RTD Project Manager: Jim Starling |
A.
Contract Information
RTD
Contract No: 37-UR-131
|
B. Company
Information
Contractor:
Lawrence Construction Company
Address: 9002
N. Moore Rd.
Littleton,
CO 80125
|
|
C. Scope
of Work
Line Segment
1 consists of civil construction including, but not limited to,
construction of three bridges and three culverts: the Belleview
Avenue railroad bridges, the Mineral Avenue railroad bridge, the
Rangeview Gulch culvert, the Lee Gulch railroad crossing culvert,
and the Slaughterhouse Gulch culvert. It also includes the railroad
trackbed grading between Belleview and Mineral avenues. Other civil
elements to be completed under this contract include construction
of retaining walls at the Littleton Station and Phillips 66 locations,
as well as construction of the LRT station platform flatwo rk, retaining
walls and drainage components in the Littleton Railroad Depression.
|
| Contract
Title: Line Segment 2
RTD
Project Manager: Jerry Nery |
|
A. Contract
Information
RTD Contract
No: 37-UR-137
|
B. Company
Information
Contractor:
Edward Kraemer & Sons, Inc.
Address: 680
Atchison Way - Suite 500
Castle Rock, CO
80104
|
|
C. Scope
of Work
Line Segment
2 consists of civil construction including, but not limited to,
construction of two bridges and a culvert: the Big Dry Creek light
rail bridge, the Tufts flyover structure, and the Lee Gulch light
rail culvert, at the completion of which the recreational trail
and water course will be restored. It also includes the railroad
trackbed grading between Oxford and Belleview avenues and the light
rail trackbed grading between Oxford and Mineral avenues. Other
civil elements to be completed under this contract include drainage,
utilities, the LRT catenary pole foundations and ductbanks, and
construction of LRT station platform flatwork, retaining walls and
underground components for the Mineral Station.
|
| Contract
Title: Line Segment 3
RTD Project
Manager: Andy Mutz |
|
A. Contract
Information
RTD Contract
No: 37-UR-135
|
B. Company
Information
Contractor:
Edward Kraemer & Sons, Inc.
Address: 200
S. Colorado - Suite 200
Denver, CO 80222
|
|
C. Scope
of Work
Line Segment
3 consists of civil construction including, but not limited to,
construction of five bridges: the Oxford Avenue light rail bridge,
the Oxford Avenue railroad bridge, the Hampden Avenue light rail
bridge, the Hampden Avenue railroad bridge, an d the Dartmouth Avenue
railroad bridge. It also includes the railroad trackbed grading
and drainage between Asbury and Oxford avenues.
|
| Contract
Title: Line Segment 4
RTD Project Manager:
Chris Horn |
|
A. Contract
Information
RTD Contract
No: 37-UR-118
|
B. Company
Information
Contractor:
PCL Civil Constructors, Inc.
Address: 680
Atchison Way - Suite 500
Castle Rock, CO
80104
|
|
C. Scope
of Work
Line Segment
4 consists of civil construction including, but not limited to,
construction of four bridges: the Iowa Avenue railroad bridge, the
Iowa Avenue light rail bridge, the Iowa Avenue light rail flyover
structure, and the Mississippi Avenue railroad bridge. Also included
is the railroad trackbed grading between Alameda and Asbury avenues
a nd the light rail trackbed grading between Broadway and Oxford
Avenue. Other civil elements to be completed under this contract
include demolition of the existing northbound and southbound bridges
over Iowa Avenue and demolition of the Machine Mart buildi ng. The
civil contractor will also perform drainage, utilities, the LRT
catenary pole foundations and ductbanks, and construction of LRT
station platform flatwork, retaining walls and underground components
for the Oxford, Hampden and Evans stations.
|
| Contract
Title: LRT Signals/Communications
RTD Project Manager: Samer Tamimi |
|
A. Contract
Information
RTD Contract
No: 38-UR-102
|
B. Company
Information
Contractor:
Harmon Industries
Address: PO
Box 600
Grain Valley,
MO 64029
|
|
C. Scope
of Work
The Contractor
to design, furnish and install a fully functional automatic block
wayside signal system along the entire light rail alignment from
South Broadway to Mineral Avenue. This work shall also in clude
modification of the existing interlock at South Broadway to accomodate
the light rail extension and construction of a new interlock at
Mineral Avenue. This work includes but is not necessarily limited
to hardware, assembly and equipment procurement and design, and
its subsequent field fabrication, material, appurtenances and incidentals
necessary to complete the signal system.
|
| Contract
Title: Operations Facility Expansion
RTD Project Manager: Jim Starling |
|
A. Contract
Information
RTD Contract
No: 38-UR-107
|
B. Company
Information
Contractor:
K.E.C.I. Colorado, Inc.
Address: 5750
W. Airport Rd
Sedalia,
CO 80135
|
|
C. Scope
of Work
The Operations
Facility Yard Expansion consists of civil construction including,
but not limited to, construction at Navajo Street and at the Mariposa
yard. The work for Navajo Street includes demolition and replacement
of pavement and curb and gutter, installation of fencing and an
electric gate, storm drainage improvements, construction of a sanitary
sewer line, and abandonment of an existing sanitary sewer line.
The work for Mariposa yard includes dem olition of concrete track
apron, subgrade preperation for 4 storage tracks, construction of
retaining walls and ballast curb, and installation of catenary pole
foundations, ductbanks, conduits, handholes, lighting foundations
and fixtures.
|
| Contract
Title: Railroad Relocation - UPRR
RTD Project Manager: Jerry Nery |
|
A. Contract
Information
RTD Contract
No: 17-UR-142
|
B. Company
Information
Contractor:
Union Pacific Railway Company
|
|
C. Scope
of Work
Work to be performed
by the UPRR forces includes, but is not limited to, furnishing all
materials and labor necessary to temporarily and permanently relocate
its railroad track and facilities to accommodate RTD's construction
of a double-track light rail system from RTD's existing I-25 & Broadway
Station to Mineral Avenue.
|
| Contract
Title: Railroad Relocation - BNSF
RTD Project Manager: Jerry Nery |
|
A. Contract
Information
RTD Contract
No: 17-UR-143
|
B. Company
Information
Contractor:
Burlington Northern and
Santa Fe Railroad Co.
|
|
C. Scope
of Work
Work to be performed
by the BNSF forces includes, but is not limited to, furnishing all
materials and labor necessary to temporarily and permanently relocate
its railroad track and facilities to accommodate RTD's construction
of a double-track light rail system from RTD's existing I-25 & Broadway
Station to Mineral Avenue.
|
|