Progress continues at Kalamath Crossing with track tamping and surfacing
Last weekend, crews reconstructed the light rail crossing at Kalamath Street and reopened two lanes of traffic on Saturday evening. This week’s Downtown Rail Reconstruction Project update highlights crews continued work this week, tamping and surfacing over 1,000 linear feet of track, completing 6 welds, and performing rail-to-earth testing.
For the latest project information, including maps, timelines and detours, visit rtd-denver.com/railproject. Weekly status reports are posted on Fridays and include photos, maps and illustrations. Questions can be directed to R[email protected] or by calling the project hotline at 720-902-8817. Customers can also find details about Service Changes and sign up for Service Alerts to stay informed about construction-related impacts.