A light rail train near the Colfax at Auraria Station with the city in the background.

Downtown Rail Reconstruction Project

Week 2: September 6 - 12, 2025

The following work and activities were safely and successfully completed:

  • Temporary construction fencing and overhead catenary wire protection were put in place
  • Equipment, materials, and temporary facilities, including portable restrooms, were brought to work site
  • Installation of project information banners near the work site
  • Non-RTD utilities were located
  • All necessary permits were obtained
  • Community outreach meetings were held with community groups, and the project webpage was updated
  • A project hotline was established for the public to share their concerns and ask questions, and the phone number is 720.902.8817

Additionally, coordination with Denver’s Department of Transportation and Infrastructure (DOTI) took place on Tuesday, Sept. 9, and Wednesday, Sept. 10, to finalize demolition limits and review traffic and train signal equipment. Sidewalk access along Kalamath Street and near the Colfax at Auraria Station will remain open until Monday, Sept. 15.

Project Status Report: Week 2

-

IMPORTANT: Demolition of existing concrete and rail materials is planned to start on Monday, Sept. 15. A double, right-lane closure on southbound Kalamath Street between Speer and Colfax will go into effect. Drivers traveling south on Kalamath can use the left two lanes and still turn right at Colfax Avenue. Pedestrians and bicycles detour to either 9th Street or Speer Boulevard to navigate around the construction zone. Click here to access a map of the construction-related detours.

Weekly Status Updates

Throughout the duration of the Downtown Rail Reconstruction Project, weekly status reports will be posted to the project webpage on Fridays. The reports include photos, maps, and illustrations. Follow-up questions can be sent to [email protected].

Week 1: Sept. 2-5, 2025

The following activities were safely and successfully completed this week:

  • Pre-construction work began at the Kalamath Street light rail crossing
  • Placement of advance warning variable message signs (VMS)
  • Track materials inventory
  • Underground utility location for RTD-owned utilities
  • Pre-construction surveying

Additionally, crews began work to repair and upgrade platform signage at the Colfax at Auraria Station.

Project Status Report: Week 1

Week 2: Sept. 6-12, 2025

The following work and activities were safely and successfully completed this week:

  • Temporary construction fencing and overhead catenary wire protection were put in place
  • Equipment, materials, and temporary facilities, including portable restrooms, were brought to work site
  • Installation of project information banners near the work site
  • Non-RTD utilities were located
  • All necessary permits were obtained
  • Community outreach meetings were held, and the project webpage was updated
  • A project hotline was established for the public to share their concerns and ask questions, and the phone number is 720.902.8817

Additionally, coordination with Denver’s Department of Transportation and Infrastructure (DOTI) took place on Tuesday, Sept. 9, and Wednesday, Sept. 10, to finalize demolition limits and review traffic and train signal equipment. Sidewalk access along Kalamath Street and near the Colfax at Auraria Station will remain open until Monday, Sept. 15. At that time, pedestrian detours will begin.

Project Status Report: Week 2

Project Overview

In May 2024, RTD began a multi-phased project to reconstruct its oldest light rail infrastructure. This major reconstruction project is the first of its kind in RTD’s history and will ensure the long-term integrity of the network.

After more than 30 years of continual operation, RTD is investing in its oldest rail infrastructure to ensure the long-term integrity of the network. Light rail service began in Denver on October 7, 1994, with 5.3 miles of track connecting 30th Avenue and Downing Street to Interstate 25 and Broadway. Much of today’s downtown track infrastructure, commonly referred to as the Downtown Loop, has been in place since the line was first constructed and opened for service. This original section of track has expanded over the years to now serve 10 rail stations on the D, H, and L lines, with street-level trains operating adjacent to pedestrians and vehicular traffic. More than 300 light rail trains circle the Downtown Loop every day, so it is critically important RTD maintain this asset in a state of good repair for the next 30 years.

Overview of the Downtown Rail Reconstruction Project

Project Timeline

The numbering of RTD’s four project phases does not necessarily correspond to their order of importance, and work will be completed out of numerical sequence. The four phases were developed to denote the specific sections of rail that will be reconstructed throughout this multi-year project. During each phase of the project, light rail services in the Downtown Loop will be impacted.

Phase One: 2024, Phase Three: 2025, Phase Two: 2026, and Phase Four: 2026

Rail Disruption Map

Effective August 31, 2025

Rail Disruption Map showing D Line trains rerouting to Denver Union Station and H Line trains turning at Southmoor Station.

Project Phases

Phase One: Five Key Intersections

Timeline: Completed in 2024

Phase One of RTD’s Downtown Rail Reconstruction Project was successfully completed ahead of schedule on August 29, 2024. The first phase focused on reconstructing light rail track and infrastructure at five key intersections in the Downtown Loop:

  • Broadway and Welton
  • 15th and California streets
  • 15th and Stout streets
  • 17th and California streets
  • 17th and Stout streets

Each intersection received a full-depth reconstruction to improve safety and mobility, address deteriorating transit infrastructure, and protect the agency’s investment in its key transportation assets.

Map of the Downtown Loop showing completion of Phase One

Phase Two: Downtown Loop Midblocks

Timeline: 2026

Phase Two will focus on a full-depth reconstruction of the rail segments between the intersections where work was completed in 2024. D, H, and L line trains will be impacted.

Map of the Downtown Loop showing the scope of work for Phase Two

Phase Three: Kalamath Crossing and Colfax Alignment

Phase Three Overview

Phase Three will focus on a full-depth reconstruction of the light rail track that runs parallel to Colfax. It does not include any segments of track near the Colorado Convention Center, as they were subject to previous targeted repairs.

  • Phase Three – Part A: Kalamath Crossing
  • Phase Three – Part B: Colfax Alignment
Map of the Downtown Loop showing the scope of work for Phase Three

Part A Timeline: Sept. 2 - Nov. 27, 2025

This phase of the Downtown Rail Reconstruction Project will be subdivided into two separate windows, with crews first addressing the at-grade crossing at Kalamath Street. Work on the Kalamath Street Crossing is planned to commence on Tuesday, September 2, and work will end on or before Thursday, November 27.

Kalamath Street Crossing

Map showing work taking place along Phase Three, which is the Kalamath Street light rail crossing

Temporary maintenance was previously completed in 2024 to stabilize the rail base until a full-depth reconstruction of the crossing could be completed.

Planned Service Disruptions
During this phase of the project, all D Line trains will be rerouted to Denver Union Station. The H Line will be truncated to Southmoor Station, and customers continuing downtown will need to connect to an E Line train. The E and H lines will maintain 15-minute frequencies to support customer transfers. The L Line will be temporarily suspended during the project, and bus Route 43 will provide customers with continued connections along the corridor.

Graphic outlining the work to be completed at Kalamath Street crossing. The illustration shows a rail detour map, calendar of work, and outlines customer benefits of reduction in unplanned maintenance.

Part B Timeline: 2026

Work along the remaining light rail track in Phase Three will commence in 2026. This subsection of the phase will include a full-depth reconstruction of the track that runs adjacent to Colfax, near the Auraria Campus.

Phase Four: Welton Street Corridor

Timeline: 2026

The final phase of the Downtown Rail Reconstruction Project will include a full-depth reconstruction of the existing light rail track along the Welton Corridor, between the Welton and Broadway intersection and RTD’s 30th•Downing Station. This phase will evaluate station accessibility and replace high blocks at existing L Line stations.

Map of the Downtown Loop showing the scope of work for Phase Four

Watch the presentation above to learn more about RTD's construction downtown.

Customer Tools

Frequently Asked Questions

Get answers to frequently asked questions about the Downtown Rail Reconstruction Project

Frequently Asked Questions

Service Alerts

RTD encourages customers to sign up for Service Alerts to receive text and email notifications about future and real-time disruptions that impact specific bus routes, rail line, stop or station.

Subscribe for Updates

Next Ride

Customers are also encouraged to use the Next Ride web app to plan trips, view active Service Alerts, and see bus and train locations in real time.

Access Next Ride Here

Customer Care

For additional route and schedule information, or questions on impacts to service, RTD’s Customer Care agents are available 6 a.m. to 8 p.m. on weekdays, and 9 a.m. to 6 p.m. on Saturdays, Sundays and holidays by calling 303.299.6000. For Spanish, press 2. For assistance in all other languages, please tell the Information Specialist what language you speak and stay on the phone while they connect to an interpreter.

Request a Translation

Need RTD materials translated into a specific language beyond Spanish? To the extent possible, RTD will provide the translation that you need! Click here.

Partner Briefing

Completed Work

53956661952
53956665852
53957562581
53956665057
53957816578
53956667697